At a Tuesday site meeting, the scanners for a new fulfillment center are still marked “on track.” The supplier's order page says they will arrive the following Wednesday. Nobody is especially worried. The person arranging staff training is the first to ask a useful question: if the shipment slips, what's the last day we can get a working set of scanners somewhere else?
The answer is Friday at noon. After that, the rental company can offer the equipment, but can't commit to delivering it in time for training. Tuesday's status update was accurate. It left out the date the team needed to make a choice.
A risk register records what might happen, what it would affect, who is watching, and when the team will act. It earns its place alongside a project plan when it helps people use the time they have left.
Copy this risk register template
A shared document or spreadsheet is enough to get started. Give each risk an ID people can refer to in a conversation, and keep dates specific enough that two people would check at the same time. The Canada School of Public Service's risk register shows how a more comprehensive register captures triggers, accountable owners, and action plans.
Risk ID and short name:
What might happen:
Consequence for the project:
Owner:
What we know today (with source and date):
Likelihood and impact:
Trigger for a decision or action:
Last useful date to act:
Mitigation we can start now:
Contingency if the trigger is met:
Who can authorize the contingency:
Next check and current status:
Decision, issue, or task links:Likelihood and impact help when the team has several risks to review. A short explanation can be more useful than converting weak evidence into precise numbers. “Possible: delivery date exists, but no dispatch confirmation” gives a reviewer something to check. “Likelihood: 35%” invites an argument about a number the team probably can't substantiate. When you do have historical data, use it and explain what it covers.
A risk is still uncertain. If the supplier has already told you the equipment won't arrive in time, the delay is an issue with work attached to it. Keep the risk entry and link it to that work. Later, when someone asks why the team paid for rentals, they'll be able to follow the record back to the information they had at the time.
Tuesday: Put a date on the fallback
The fulfillment center will train its first shift on Thursday morning. Six working scanners are enough to train people in pairs. The plan calls for twelve, but training doesn't depend on having all twelve. Once the team sees that distinction, it can price a smaller rental and consider opening the site in stages if fewer devices arrive.
Nadia, the site operations lead, volunteers to own the risk. She asks the supplier for a carrier reference and confirmation that at least six devices are in the shipment. She also asks the rental company to hold six compatible units until Friday at noon. A colleague checks whether the rental units can run the warehouse app. The work for Tuesday is to keep the fallback open.
| Field | R-07: Scanners may miss training |
|---|---|
| What we know | Supplier portal shows Wednesday delivery; no carrier reference as of Tuesday. |
| Consequence | With fewer than six compatible units, Thursday's first shift can't finish hands-on training as planned. |
| Owner and check | Nadia checks dispatch and quantity again on Friday at 10 a.m. |
| Trigger | If a Wednesday delivery for at least six units is still unconfirmed at Friday's 10 a.m. review, take the rental option to the budget owner. |
| Last useful date | The rental company releases its hold at noon Friday. |
| Response | Verify compatibility and reserve six units now; confirm the rental order only after approval. |
The trigger and deadline solve different problems. At ten, Nadia needs to make a recommendation. At noon, a supplier stops holding equipment. Putting both events at noon would turn a manageable decision into a race to find the person with purchasing authority.
The same reasoning applies outside logistics. A team building a feature might still have two weeks until launch, but only three days before the translation vendor needs the final text. Ask which opportunity disappears first. That is often the date worth adding to the register.
Friday: Decide using the evidence you actually have
On Friday morning the supplier portal still says Wednesday. A salesperson has emailed that the shipment is “moving through dispatch.” Nadia asks whether the carrier has picked it up. It hasn't. There's no carrier date or confirmed quantity by the ten o'clock review.
The register tells her what to do with that uncertainty. She sends the budget owner the updated supplier note, the rental quote, the compatibility check, and a short account of what would happen if they waited. She includes the cost of six rentals and the training slots the team would have to move if no equipment arrived. With those two consequences visible, the budget owner approves the order before the hold expires.
Keep the response proportionate. In another project the equipment might be easy to borrow from a nearby office, or the training date might be cheap to move. The same trigger could lead to a different response. The useful record shows why this team chose this fallback on this Friday.
A short decision entry might read:
Approved a rental of six compatible units on Friday at 10:35 a.m. The supplier displayed Wednesday delivery but could not provide pickup, quantity, or a carrier commitment. The rental hold expired at noon. Compare the rental cost with the current training plan when reviewing the decision.
Link that entry to R-07 and to the ordering task. A project decision log is a good place to preserve the rationale if someone changes the plan later. Keep the register concise enough to use during a meeting; the details can live in the linked evidence and decision.
After training: Close the risk without rewriting the history
The rented units arrive on Tuesday and the team uses them to set up and test the training stations. Eight purchased scanners arrive on Wednesday afternoon, as the portal had said they would. Training goes ahead on Thursday. Someone looking only at Wednesday's delivery might conclude the rental was unnecessary.
Go back to the Friday record. At that point the team couldn't verify delivery, and waiting would have removed the cheaper fallback. The outcome is now known, but the Friday decision still needs to be judged on the choices available then. Closing the risk can be brief: record that eight units arrived, record the actual rental cost, and link the completed training check. Keep “Wednesday delivery confirmed” out of the earlier entry.
The register also gives the team a concrete improvement for next time. Ask for a carrier confirmation and shipment quantity before the contingency deadline, perhaps as part of the supplier check a week before training. Add that to the next site's plan. It will do more good than telling everyone to “manage delivery risks proactively.”
Review the risks that can still change the plan
If a register has twenty entries, opening all twenty during a weekly call is a poor use of time. Start with the ones approaching their last useful action date, the ones whose evidence changed, and the ones with no accepted owner. The discussion becomes shorter because everyone can see which decision is coming up.
A vague entry such as “training delays” is often a signal to ask one more question. Which first shift? What needs to be present for the training to work? What can be done without it? Depending on the answer, you may uncover a risk that deserves its own row or an ordinary planning task you can finish today. Similarly, if a risk has lost relevance because the project changed, close it with a sentence about what changed. Otherwise it stays on the list and competes for attention with real decisions.
Use an agent to prepare the review
Give the agent the current register and the latest project updates you want it to compare. Have it return the risk ID, the new evidence, and a question for the owner. Ask it to distinguish a met trigger from an unconfirmed one. In the scanner example, “moving through dispatch” does not establish pickup. The source and its time matter more than how confidently the status update reads.
You can keep this work in a private Swarm Space with the register saved as an Artifact and the checks tracked as Tasks. Connect an agent to the relevant Space and give it the source records for a small review. Have it prepare suggestions before changing the register or performing any work. People still confirm the evidence and authorize consequential responses. This setup relies on updates the team supplies or makes available to the agent.
Pick a risk from a project you're running now and ask the team one question: what is the last point at which we can still choose? Build the first entry around the answer. If somebody hears the date and starts checking a supplier, changing a test plan, or reserving a fallback, the register is already doing useful work.