Project decision log template: How to record decisions that change

Use a copyable project decision log to keep current commitments, their sources, and the follow-up work easy to find when a team changes course.

Purple and yellow-green liquids run through narrow channels in a clear laboratory cassette.

A project decision log records what your team agreed to, who made the call, and what evidence they used. For a decision that changes, keep the old entry and point it to its replacement. Someone joining the project later should be able to tell what applies now and why.

Suppose a software company plans to acknowledge urgent weekend support requests within two hours. The plan depends on a vendor monitoring the queue all weekend. A month later, the vendor confirms that it can cover Saturdays but has no Sunday coverage. The team revises the commitment. By Monday, the old wording is still in a customer email draft, the onboarding checklist, and a note an AI agent has been using. Which version should those people and tools work from?

A project decision log template you can copy

Keep an index with the decision, status, owner, date, and replacement reference where one exists. Give important decisions their own entry with enough context to understand the choice. Copy this entry into the place your team already checks for project information.

FieldWhat to record
ID and titleA short reference and the choice itself, such as D-07: Use the standard weekend response target.
Status and effective dateProposed, current, superseded, or withdrawn, and when the decision starts to apply.
ScopeThe projects, customers, environments, or time period the decision covers.
Owner and approvalWho maintains the entry and who made or approved the decision.
Reason and sourceThe decisive constraint, a relevant alternative you passed on, and links to supporting records.
Replaces or replaced byThe decision ID and link in either direction, when applicable.
Follow-up and review triggerWhat has to change, who owns it, and what would cause the team to reconsider.

The index gives a reader a quick way to find the current entry. The entry gives them the reason to trust it. For decisions with several contributors, Atlassian's DACI template is a useful reference for identifying who drives the decision and who approves it. A small project can start with one named owner and one named decision maker.

Light from a low industrial facility spills onto a terrace at night.

What two linked entries look like

The following records are fictional. The coverage agreement, availability note, and approval refer to example source records a team would link in its own log.

FieldD-07: Acknowledge urgent cases in two hours all weekendD-12: Limit the two-hour target to Saturday coverage
StatusSuperseded by D-12Current from May 16
ScopeUrgent cases in the new support plan; Saturday and SundaySame plan and urgency; Saturdays from 09:00 to 17:00 ET. Requests received less than two hours before coverage ends, and requests outside the window, follow the existing response target.
ReasonThe coverage plan assumed staffed triage on both days.The vendor confirmed Saturday staffing only. The team considered arranging Sunday cover, but no Sunday responder was assigned.
Record ownerSupport operations lead.Support operations lead.
Source and approvalOriginal coverage plan; March 30 approval from the support lead.Vendor availability note; May 12 approval from the support lead.
Follow-upOriginal onboarding draft and response guidance now need review under D-12.Support operations updates the checklist and agent brief. Account leads review wording before anyone sends a new commitment.
Review triggerSee the replacement entry.Revisit when a Sunday rotation has a named owner and confirmed coverage.

Notice the late Saturday case. At 16:30, with the shift ending at 17:00, a reader might assume the two-hour target still applies. Writing the rule explicitly avoids leaving that choice to whoever happens to be answering. If the team has not decided what to do in that window, record an open question and leave it with the support lead.

The current decision governs new work from its effective date. It does not rewrite what a customer was already promised. Someone authorized to handle that customer relationship should check any previous commitment separately.

Update the work that depended on the old decision

Saving D-12 fixes the log. It leaves the team's documents and saved agent instructions as they were. Start the follow-up by listing what still cites D-07: the onboarding checklist, the pending email, and the support agent's brief. Identify the owner of each. Keep the old entry available so someone reviewing an earlier email can understand which decision applied at the time.

An agent can compare the two entries against supplied drafts and propose the smallest changes. Ask it to list what it inspected, show the evidence for each suggested edit, and report items it could not access. Keep the drafts and any customer communications under their usual review process. Record completed follow-up separately from work that was merely proposed.

A rail junction branches beside a ceramic actuator on dark gravel.

Test the log with someone who missed the discussion

Give a colleague the index and the underlying records. Ask: “An urgent case arrives at 16:30 ET on Saturday, May 16. Which target applies, where is that written, and which document are we still updating?” Repeat with a fresh agent session that has the necessary access.

The useful answer identifies D-12, applies the cutoff, and distinguishes the vendor's availability note from the team's approval. It also names the outstanding document only if the record shows it is still open. If the reader confidently cites D-07, check whether the replacement is visible from the old entry and whether the agent's brief still points to it. Our guide to shared project memory explains how to keep the current answer easy to find as the record grows.

A narrow crossing spans dark water between irregular patches of frost-covered tundra.

Start with one decision in Swarm

Create a private Space for a project and post one current decision with its evidence and owner. Add the earlier entry if it still appears in the work, then cross-reference the two. Ask a teammate or a connected agent to answer a specific question from the record before they act on it.